How Solar Mounting Brackets Are Manufactured
Solar mounting brackets are the steel structures that carry photovoltaic modules: posts, rails, bracing and base plates. Most are cold formed from coated steel coil, or hot-dip galvanized after fabrication. The two routes can look identical on a drawing and still behave very differently on site.
The difference comes from the order of operations. A bracket is cut, formed, punched and welded first, and only the finished assembly enters the zinc bath. Once steel is dipped, it cannot be welded or bent without destroying the coating



1. The six steps, in the order they have to happen
|
Step |
What happens |
What a capable shop checks |
|
Slitting and cut to length |
Coil is slit to strip width and cut to blank length |
Strip width tolerance, camber, coil traceability |
|
Roll forming |
Strip is formed into C, U or Z profiles |
Profile depth, lip return, twist over length |
|
Punching and notching |
Bolt holes and service holes are pierced |
Hole pitch, hole diameter, burr height |
|
Welding |
Base plates, gussets and braces are joined |
Weld size, slag removal, qualified procedure |
|
Surface preparation |
Degreasing, pickling, fluxing |
Vent and drain holes, no paint or weld slag left |
|
Hot-dip galvanizing |
Assembly is immersed in molten zinc at about 450 °C |
Drain angle, cooling, coating continuity |
Request Latest Steel Price Today
2. Why fabrication has to finish before the zinc bath
A hot-dip coating is a metallurgical bond, not a paint film. Zinc and iron react at about 450 °C and form layered alloy that no touch-up product reproduces. Three consequences cause most disputes.
Field welds expose bare steel. Any weld made after dipping must be repaired to ASTM A780 by zinc spray, zinc alloy stick or zinc-rich paint, with the repair thickness agreed in advance.
Hollow sections must breathe. Sealed tubes can burst in the bath. Vent and drain holes per ASTM A385 let zinc in and back out.
Thin sections distort. Members from 1.6 mm to 2.5 mm can warp under thermal stress, long asymmetric ones most. Fixturing and drain angle belong to the process.
3. The four defects that cause most rejections
|
Defect |
What it looks like |
What usually causes it |
How it is judged |
|
Distortion after dipping |
Rails that no longer sit flat, twisted posts |
Thermal stress on thin asymmetric sections |
Dimensional check against drawing tolerance |
|
Dull grey, rough, over-thick coating |
Matte, dark, sometimes flaking |
Reactive steel: silicon roughly 0.03–0.14 %, phosphorus above about 0.03 % |
Thickness reading plus adhesion check |
|
Bare spots and flux inclusions |
Uncoated patches, grey residue |
Poor cleaning, trapped flux, bad drainage |
Visual inspection; repair limits apply |
|
White rust |
White powdery bloom on stacked parts |
Wet storage: parts stacked tight and wrapped while damp |
Severity assessed by area; usually removable |
Reactive steel is the one that surprises buyers. A thick coating is not automatically good: beyond roughly 150 µm to 200 µm the alloy layers turn brittle and can flake under handling. Bath chemistry and immersion time are adjusted instead of letting the coating grow.
4. Coating thickness: how it is measured and accepted
ISO 1461 sets a minimum mean and a separate minimum local thickness; both must be reported. On a 3 mm bracket the mean must reach 70 µm and no single reading may fall below 55 µm. Our separate guide on galvanizing thickness carries the full table by steel thickness.
Three points matter more than the numbers themselves.
- Method. Production uses a magnetic gauge to ISO 2178; the gravimetric method of ISO 1460 is the reference when a result is disputed.
- Where readings are taken. A reference area carries at least five readings, none within 10 mm of an edge, a flame-cut surface or a corner.
- Repairs. Damage is repaired under ASTM A780 with the method agreed in advance. Total repaired area stays within 0.5 % of the surface.
One comparison needs its own warning. A Z275 coil designation means 275 g/m² across both faces together, roughly 19 µm to 20 µm per side. A batch galvanized coating on a fabricated bracket is several times heavier. The two are different products for different jobs and should never be quoted against each other.
FAQ
1.Can brackets be welded on site after galvanizing?
They can, but the weld zone loses its coating and rusts first. Plan the repair to ASTM A780 before the shipment leaves.
2.Why is my coating dull grey instead of bright?
Usually reactive steel, where silicon and phosphorus accelerate the zinc-iron reaction. It is a chemistry effect, controlled through the mill certificate.
3.Is pre-galvanized coil enough for a ground-mounted array?
It suits cold-formed rails and purlins. Posts, base plates and welded assemblies are dipped after fabrication, because sheared ends and punched holes are bare steel.
4.What documents should arrive with the shipment?
An EN 10204 3.1 material certificate, a coating report giving both mean and local values, and a dimensional report. Ask for silicon and phosphorus on the mill certificate.

Packaging and Shipping
GNEE STEEL Supply range by standard system
|
# |
Standard |
Designation system |
Base steel grades |
Coating mass designations |
Alloy system |
|
1 |
EN 10346 (Europe) |
+ZM |
Forming: DC51D+ZM, DC52D+ZM, DC53D+ZM, DC54D+ZM |
ZM100 – ZM450 (g/m², both faces) |
Zn-Al-Mg, low-Al type |
|
2 |
YB/T 4761 (China) |
+ZM |
Same base grade series as EN 10346: DC51D – DC54D (forming) and S220GD – S550GD (structural) |
ZM100 – ZM450 |
Zn-Al-Mg, low-Al type |
|
3 |
YB/T 4634 (China) |
+AZM |
DC51D+AZM, S250GD+AZM and similar |
Per standard |
Zn-55Al-Mg, high-Al type |
|
4 |
JIS G 3323 (Japan) |
-ZAM |
Commercial: SDC-ZAM, SGCH-ZAM |
Per standard |
Zn-Al-Mg |
|
5 |
ASTM A1046/A1046M (USA) |
Type 1 / Type 2 |
Type 1 (low-Al), Type 2 (mid-Al); structural levels HELAS-T 50, HELAS-T 60, HELAS-T 70 |
Per standard |
Zn-Al-Mg |
|
6 |
KS D 3860 (Korea) |
-ZAM |
SDC-ZAM, SGCH-ZAM, SDC340-ZAM, SDC400-ZAM, SDC440-ZAM |
Per standard |
Zn-Al-Mg |